Oracle Triggers 'Force Majeure' over Data Center Power Delays

  • Blue Owl says notice does not change financial commitments to multi-year project
  • Blue Owl has about $3 billion in equity, while Oracle pays debt costs, source says
  • Oracle says Project Jupiter remains on its planned schedule

(Reuters) - Oracle issued a "force majeure" notice to a Blue Owl unit, the developer of a large New Mexico ‌data center, citing potential delays in securing power for the project, a person familiar with the matter told Reuters on Thursday.

Shares of Oracle were down 3.3%. The source said that securing power for the site is Oracle's responsibility under the contract.

Oracle cannot terminate the lease under any circumstances, the source said, ​adding that alternative asset manager Blue Owl has about $3 billion in equity in the project, with Oracle responsible for paying ​the debt costs.

Companies typically invoke force majeure to free themselves from contractual obligations when problems arise ⁠beyond their control, a move that can raise concerns among lenders and investors.

Rather than exiting as the main tenant, Oracle is ​attempting to delay payments should the data center dubbed Project Jupiter get derailed and fail to come online in 2028 as planned, ​according to a report by Bloomberg News, which first reported the development.

Oracle did not immediately respond to a Reuters request for comment. "Project Jupiter remains on our planned schedule," the company said earlier in the day.

Blue Owl, which owns the data-center developer Stack Infrastructure, said the notice does not change ​the financial commitments to this multi-year project.

During the development stage, Blue Owl earns a 9% yield on its equity, the source ​said, adding that upon completion of the project, the levered yield is expected to be around 11%.

By invoking force majeure, Oracle extends the period ‌during which ⁠it pays Blue Owl the lower development-stage rent. Blue Owl will still receive the higher rent for the originally planned duration, but its start will be delayed, according to the source.

The 1,400-acre Project Jupiter campus, which secured $18 billion in loans from a consortium of banks, according to media reports, is part of Oracle's broader agreement with OpenAI to provide AI computing capacity.

The data center campus has ​reportedly faced multiple infrastructure setbacks, ​including delays to a planned ⁠natural-gas pipeline and legal challenges over water and air-quality permits.

The project is a part of Stargate, an initiative to build AI infrastructure in the US under a $500 billion investment commitment involving OpenAI, SoftBank ​Group and partners including Oracle.

The massive AI infrastructure build-out has faced mounting challenges, as developers ​race to secure ⁠power and other resources while managing the enormous costs of deploying computing capacity for partners such as OpenAI.

Growing opposition from the public has made data centers a political flashpoint, with communities around data center projects raising concerns over their impact on local supply of energy, water and ⁠other ​natural resources.

Brokerage William Blair said while this news intensifies worries about regulatory and ​power-related delays affecting AI deployments, it expects minimal short-term impact on Oracle.

"Practically, fiscal 2027 should not be affected, since Jupiter contributes no revenue this year."

Reporting by Isla ​Binnie and reporting by Jaspreet Singh in Bengaluru; additional reporting by Prakhar Srivastava; Editing by Devika Syamnath, Anil D'Silva and Maju Samuel